← Home

Welcome Back

Sign in to your Ask SURI account

Project Config

Dashboard
Ask SURI
Schedule & Logic
Project History
SURI Updates
Schedule Review
Delay Analysis
Linear Schedule
Portfolio
Executive Summary
SCHEDULE SNAPSHOT
--
Activities
--
--
Critical
zero float
--
In Progress
--
--
Complete
--
--
Time Elapsed
--
Key Dates Start -- | Data Date -- | Finish -- | Duration -- | Elapsed -- | Remaining -- Schedule Quality ▼
Resource Loading
Schedule Intelligence
Ask SURI
Response Depth:
Risk Report Critical Path Longest Path Lookahead Neg Float Logic Gaps Behind Schedule Long Duration Constraints Float Dist. Earned Value Milestones Health Check WBS Tree Search Activities ⚡ What-If
Tip: Ask "What if [activity] takes X more weeks?" or "What if we add a link between A and B?" to run scenario analysis
Linear Schedule
Monthly Schedule Review

Schedule Review

Monthly review of the contractor’s submission against the contract — every finding cites evidence.
Contract milestones

Required Milestones

Paste any format, upload a file, or add one at a time — SURI parses names, dates, and criticality.
Audit Inputs

Schedule + Narrative

Is this audit reviewing a contractor RESUBMITTAL (R1 or later)?
Click Run Review to start. The Scope panel shows which checks will run.

Delay Claims

Build, analyze, and document delay claims for this project
Loading claims...
Gantt
Network
+
Flatten:
STEP 1 Active
Progress As Of
Advancing the data date creates a new versioned schedule copy
Pick a date, then Change Data Date. To fix activities without advancing, use the sections below.
Current Data Date: --
STEP 2 · OPTION A Pending
Quick Update
Update activities using natural language
Type commands like: "A1010 started March 1, 75% done, 5 days remaining"  |  "Mark bridge deck pour complete, finished last Friday"  |  "Set remaining duration to 10 days for A2050"
In Progress Should Have Started Finishing Soon % Complete
Data Date: -- Change Latest Actual Start: -- Latest Actual Finish: -- -- ✓ Schedule auto-runs after every commit
Ready to accept schedule updates via natural language.
STEP 2 · OPTION B Pending
Update Schedule
Bulk update via Excel template
1. Export Template

Download the activities sheet, then fill in actual dates, % complete, and remaining durations.

2. Upload Updates

Upload any Excel with Activity ID, dates, % complete, and remaining duration — SURI auto-detects the columns.

📄
Drop .xlsx file here or click to browse
STEP 4 Pending
Out-of-Sequence
Find and fix sequence violations
STEP 5 · EXPORT Pending
Export Schedule
Re-export as XER for P6 re-import
STEP 5 · NARRATIVE Pending
Schedule Narrative
Generate update narrative for owner reporting
Reporting Period
Loading comparison options...
Compose Narrative
Standard sections
Custom focus areas
Brand Settings (Logo, Colors, Company Name)
Agency Narrative Requirements

Upload your agency's narrative spec (.pdf/.docx/.txt). SURI parses it once and stores it for the project — no need to re-upload each cycle.

Look-Ahead
Flatten:
Portfolio Resources
Peak crew demand across your projects
Ask Across Your Portfolio all projects Answers span every project you can access
Measure
Detail
Total Float
Color By
Projects
Peak Crew Demand by Discipline
Per-Crew Demand & Capacity
Type each crew’s available capacity to see the gap. A negative gap means you’re short at the peak — hire, rent, or resequence. Click a row to isolate that crew in the chart.
Schedule Change Log